ELEVATOR RENOVATION PROGRESS

Hotline: (028) 73030346
Goldview-MO@savills.com.vn
346 Ben Van Don Street - Ward 1 - District 4 - Ho Chi Minh City

Dear Value Residents,

Please be informed that, through a vote in Apartment Building Meeting 4th and contractor selection results of BOC. From 13/12/2016 contractor will tiled the wall of ground floor elevator lobby and basement elevator lobby on the following schedule:

No.

Location

Start day

Completion date

Day off

1

Ground floor Block C1

Basement floor Block C1

13/12/2016

16/12/2016

 

2

Ground floor Block C2

Basement floor Block C2

17/12/2016

21/12/2016

Sunday

18/12/2016

3

Ground floor Block B1

Basement floor Block B1

22/12/2016

26/12/2016

Sunday

25/12/2016

4

Ground floor Block B2

Basement floor Block B2

27/12/2016

30/12/2016

 

5

Ground floor Block A1

Basement floor Block A1

31/12/2016

04/01/2017

Sunday

01/01/2017

6

Ground floor Block A2

Basement floor Block A2

05/01/2017

09/01/2017

Sunday

08/01/2017

 

Contractor: Việt Thái CO., LTD.

Due to period, we are apologized for any inconvenient may cause.

Warm regards,

Management Office